Derbyshire council reappoints expert for more flood work at vulnerable business park
A Derbyshire council has reappointed a dredging and desilting expert to undertake flood mitigation work at the troubled Pleasley Vale Business Park – after it suffered storm damage and was at the centre of a disruptive evacuation.
Bolsover District Council agreed at a recent Extraordinary Executive meeting to appoint P&D Environmental Ltd to carry out a revised scheme of environmental and flood mitigation work at the business park, at Outgang Lane, Pleasley Vale, to protect its mill buildings from flood water and to carry out further urgent investigative works to mill pond dam walls and culverts.
A council spokesperson said: “The revised scope of works will undertake de-vegetation and dewatering of Mill Ponds One and Two including mechanical dredging and removal of trees undermining structural stability of dam walls [and] culverts, and improve water safety awareness around the site.”
The business park, which is managed by the council and lies on a floodplain with a flooding threat posed by the River Meden, had been identified by the council for repair work as long ago as December, 2024, with extensive renovations planned to get underway at the beginning of 2025 after damage was caused by Storm Babet in October, 2023.


Bolsover District Council previously revealed its Business Estates Manager had been working tirelessly to maintain fractured relationships with tenants but uncertainty has continued after the council issued a news alert on October 13, that businesses at the park’s Mill One building were being asked to vacate the premises due to ‘safety concerns’ before some were allowed to return by October 17 while work continued.
Staffordshire-based P&D Environmental Ltd have already undertaken bank stabilisation works to the upper part of Mill Pond One after setting up on-site work facilities at the site including a temporary bridge structure.
Works undertaken so far include repairs to the foul drainage system but culvert desilting works have been reviewed and deemed as a lower priority to desilting Mill Ponds One and Two along with the vegetation around immediate perimeters which the council says is undermining the structural integrity of the mill pond walls and culverts.
The latest work agreed to be undertaken by P&D Environmental Ltd includes a revised scheme of works to Mill Ponds One and Two to improve water flow management and flooding mitigation throughout the business park.


Bolsover District Council originally agreed in December, 2024, to use its financial reserves and implement any necessary borrowing to secure over £770,000 for flood mitigation works and repairs at the business park.
It also agreed for work to start early in the New Year of 2025 to improve flood mitigation measures and essential repairs for safety reasons, the restoration of relations with tenants and to secure redevelopment and income.
These plans identified concerns over the failure of infrastructure such as lifts at the business park, the need for new flood defence doors for the nearby electricity substation at Mill One, the need for roof replacements at Mill One and Mill Two and the need for replacement and repair work to old crumbling brickwork, corroded steel lintels and window frames and damaged stonework and copings.
The council’s renovation plans at the historic site also included improving the dam wall and making sure the Mill One pond could capture an increased level of water from the River Meden to slow the flow downstream into the Mill Two building and under the culverts in the Mill Three building.
Other targeted work included improvements for a fire alarm system, for the drainage network and installing a new lift in Mill Two.
Bolsover District Council recognised the need for a full intrusive structural survey to locate a potential culvert under Mill Three as well as a structural survey for Mill Three’s outbuildings which had seen visible signs of movement as well as work to renovate and reuse the two Gatehouse properties, Gardener’s Cottage and Coach House, which are on the Listed Buildings at Risk register.
The council also agreed in June, 2025, to approve the works to undertake the desilting of culverts and repairs to foul drainage systems at Pleasley Mills to a value of £608,537.
However, the cost of undertaking the latest, revised scope of works is £861,474, so the council has approved and agreed at a meeting in December to use £603,537 of the previously approved £608,537 of funding and to allocate a further £257,900 from its reserves for this scheme to be undertaken by P&D Environmental Ltd.
A council spokesperson added: “Not undertaking the works would constrain essential works to maintain [the] structural integrity of mill pond walls and culverts that in turn support the mill buildings and water management in the event of further severe weather events experienced in periods of flooding.”
The council felt that to seek a different contractor would lead to increased costs with the need for new work facilities at the site and it is eager for the work to be completed without delays before any worsening weather and to ensure it complies with the Environment Agency’s permit and maintenance exemption period.
Pleasley Vale Business Park, on the edge of Mansfield, features 198 units over three mills and outlying buildings, including the Dye House, Stable Block, and the Mill Three Courtyard.
During Storm Babet, in 2023, the River Meden overflowed and flooded parts of the site causing extensive damage to properties and land including flooding to the ground floor of Mill One and damage to an electricity substation with the financial and economic impact being felt by businesses.
The history of the Mills dates back to 1784, according to the council, and since then they have been used as a cotton spinning mill, munitions factory and now as a business park.