Derbyshire residents raise concerns about proposed multi-million pound scheme for a massive underground CO2 pipeline from the Peak District
Derbyshire residents have raised concerns about a proposed multi-million pound scheme for a massive underground CO2 pipeline from the Peak District.
Peak Cluster, which is a collaboration between cement and lime producers in Derbyshire and Staffordshire, has outlined plans for a £59.6m project that aims to build a 121 mile underground pipeline to carry captured carbon dioxide from four cement and lime producers across sites in Derbyshire and Staffordshire out to the Irish Sea.
Chartered surveyors and planning consultants Wilson Fearnall are already encouraging engagement with the consultation among landowners, farmers and residents and some have already raised concerns.
Laura Stark, of Hope Valley, said: “Residents are angry and frightened, with many posed with the threat of losing their homes, land, and farmland to a big business venture masquerading as environmentalism.


“Peak Cluster plan to dig a ‘124 miles’ CO2 pipeline from the Peak District out to the Irish Sea, through the Wirral, and pump CO2 into the seabed. This is not a good thing.”
Residents have set up a Facebook page; ‘Peak Cluster CO2 Pipeline in High Peak’ which has over 600 members and a petition has been launched asking the Government to pause all UK offshore CO₂ storage projects until a full independent safety, environmental and legal assessment is completed.
Peak Cluster has stated it aims to oversee the project to capture carbon dioxide from four cement and lime producers across sites in Derbyshire and Staffordshire to help to secure the future of Britain’s cement and lime industries while safeguarding and creating jobs and ensuring a reliable, ‘homemade’ supply of essential materials.
Proposed work plants in the scheme include Buxton Lime’s Tunstead lime plant, at Tunstead Quarry, off Waterswallows Road, in Buxton, Breedon’s Hope cement plant, at Pindale Road, in the Hope Valley, Tarmac’s Tunstead cement plant, at Waterswallows Road, Tunstead House, in Buxton, and Holcim’s Cauldon plant between Cauldon and Waterhouses villages in Staffordshire.
If approved, the plans will see carbon dioxide transported and stored permanently beneath the East Irish Sea which Peak Cluster claims will help to secure the future of Britain’s cement and lime industries while safeguarding and creating jobs and ensuring a reliable, ‘homemade’ supply of essential materials.
John Egan, CEO of Peak Cluster Ltd, has said: “Peak Cluster is focused on securing a sustainable future for the cement and lime industry. Together with the Morecambe Net Zero Project, the UK’s biggest carbon store, we will capture, transport and store CO2 to support industry to thrive in a low carbon future.”
Derbyshire County Council said it has been keen to take part the first consultation ending on February 27 and the Peak District National Park Authority says it also aims to continue to be actively involved in the process hoping to balance the benefits of carbon capture against any potential impact to the national park.