County Council to invest £4.5M in Derbyshire schools


Schools across Derbyshire will receive a share of £4.5m towards the cost of creating more space and making the learning environment better for students.
A total of 18 schools will receive a cash injection from Derbyshire County Council towards on-going or new projects to modernise or expand following decisions made by Cabinet.
Councillors agreed to allocate £3.1m from the Children’s Services Capital Budget to 10 schools to improve the condition of buildings including roofing, new windows, boilers or re-wiring.
This modernisation work is needed to ensure schools can continue to teach children safely in spaces that enable them to get the best from their learning.
Cabinet also agreed to give funding totalling £1.143m to five schools to create extra classroom space or provide multiple-purpose spaces in areas where there is greatest demand for places.
This money has come from Section 106 agreements – where developers contribute towards the cost of creating infrastructure, such as schools, when building new homes.
Meanwhile, spending of a further £155,000 has been delegated for specific one-off projects at three schools including a new veranda, drainage and electrical work.
Councillor Simon Mabbott, the council’s Cabinet Member for Send and Education, said: “I’m delighted that this funding has been agreed to create extra school places and provide an environment that better supports pupils’ learning.”
Below is a full list of schemes being funded by the county council:
Children’s Services Capital Budget Modernisation Programme
- Thornsett Primary School, New Mills: roofing; £450,000
- Parwich Primary School, Ashbourne: replacing windows and damp works; £115,000
- Ripley Infant School: roofing; £775,000
- Brockwell Primary School, Chesterfield: roofing; £600,000
- Northfield Junior School, Dronfield: rewire; £330,000
- Etwall Primary School: boiler and plantroom work; £175,000
- Longmoor Primary School, Long Eaton: plantroom replacement tanking; £245,000
- Pinxton Nursery School: rewire; £120,500
- Croft Infant School, Alfreton: window replacement; £275,000
- Killamarsh Infant School: roofing in corridor link area; £75,000
Section 106 Allocations
- Heanor Gate Spencer Academy: contribution to existing expansion project; £219,724
- Eureka Primary School, Hartshorne: contribution to three classroom block; £384,131
- Woodthorpe Primary School: New project for new building for multi-purpose use including a library, intervention and teaching space; £159, 586
- Belper School and 6th Form: contribution to expansion project; £107,573
- Langley Mill Academy: internal re-modelling to create three extra classrooms; £272,483
Delegated Approval
- Highfields School, Matlock: veranda works; £20,000
- Duffield Meadows: sustainable drainage system; £75,000
- Wilsthorpe School, Long Eaton: To separate electricity supply; £80,000